The Project
Impressions from the project process
Project Information
Requirements
Tight deadlines up to completion
Solutions
ACS self-climbing units with VARIO GT 24 Wall Formwork for the rectangular building core combined with crane-climbing CB 240 Climbing Scaffold.
Customer benefits
Short construction time in 3-day cycle for one storey with an area of 1,350 m²
Considerable amount of crane capacity saved thanks to ACS self-climbing technology
PERI ACS is unbelievably quick and extremely safe. We were able to save a considerable amount of crane capacity thanks to the self-climbing technology. That is a huge advantage on construction sites like these.
P. Schneider and G. C. Christofides
Site Manager | Project Manager